Alfred Hospital, Melbourne
Another quality project by AAH Contracting
Location
Melbourne, Victoria
Completion
February 2019
Safety
Highest Safety Standards
Download
Download The Case Study
Project Overview
The Alfred is Melbourne’s oldest hospital still operating on its original site. AAH was awarded friable asbestos removal and minor demolition works at the Alfred Hospital.
- Remove friable asbestos sprayed beam insulation and associated overspray across the entire ward
- Remove asbestos vinyl floor tiles across the entire ward as well as on the ground floor
- Remove contaminated synthetic mineral fibre pipe insulation
- Respray all beams with a non-hazardous alternative to meet fire rating requirements
Critical Factors/Challenges
- Co-ordinating multiple trades across the site
- Keeping the noise to a minimum so as not to disturb the hospital operations
- Removing the large amount of contaminated waste from the work area and through the hospital during operational hours
- Building a large, intricate work enclosure through the ward
Outcomes
- All waste was successfully moved from the work enclosure, through the hospital and to an EPA licensed disposal site without impacting workflow within the hospital
- The job was successfully completed under a tight time frame
- A dedicated project manager was on site to oversee all works throughout the duration of the project
- Works were externally audited against our AS/NZS 4801 safety certificate with 0 non-conformances found on site